Turn Key & Major Projects |
|
Location: Africa, Project value: Excess of £5 million.
Sugar factory re-furbishment, supply & installation of centrifugal machines. Location: UK, Project value: Excess of £1 million.
Supply, install & commission watertube boiler including all instrumentation & automated control systems. Location: Kosovo, Pristina, Project value: Excess of £300,000.
Supply secondhand shell steam boilers, convert to high pressure hot water & refurbish totally UK, liaise with government appointed agency for shipping by air to Kosovo, supply of TIBS site labour to install & fully commission boilers on site. Location: UK, Project value: Excess of £120,000.
Stripping boiler furnace of asbestos & refractory, installing new refractory, supply & install new furnace side wall, rear wall & roof elements, commission boiler & cure refractory, carry out annual inspection work on refurbished boiler & 4 other boilers on site. Full CDM regulations, method statements, risk assessments & hazard identification were of major importance in the winning & running of this project. Location: Africa, Project value: Excess of £2 million.
Supply of spares & labour to refurbish boilers & ancillary plant at 3 sugar factories. |
|
![]() Typical Cane Sugar Factory |
![]() Steam turbine, installed by TIBS engineers |